• References - in last five years


Project title

Client

Name of partner(s)

Start/End Date

Status

EPCG Metering Project Consultant for the Project Implementation Unit

Public Enterprise Elektroprivreda Crne Gore (EPCG), Montenegro

CESI, Italy

May 2011 / December 2014

on-going

Environmental and Social Impact Assessment for South Stream Gas Pipe-Line through Serbia

DIEM, Russia

 

March 2011/ June 2011

on-going

EPS Metering Project Consultant for the Project Implementation Unit (PIU)

Public Enterprise Elektroprivreda Srbije (EPS), Serbia

CESI, Italy

January 2011/ July 2013

on-going

Wind Potential Assessments–Crni Vrh Project

Decotra Srl, Milano, Italy

 

September 2010/ December 2011

on-going

Due diligence of PSP Djerdap III in today conditions

RWE, Germany

 

July 2010/ February 2011

completed

Investment Opportunities on Renewable Energies in Montenegro

A2A, Italy

HEMERA Technologies, Montenegro

June 2010/ October 2010

completed

Conceptual Design of the HPPs on Velika Morava River within integral use of available Velika Morava River Waters

RWE, Germany

 

May 2010/ November 2010

completed

Consulting Services During Elaboration of Technical Documentation for Construction of Petroleum Products Pipeline System through Serbia

JP Transnafta, Serbia

 

February 2010/ May 2011

on-going

Study on the Potential for Climate Change Combating in Power Generation in the Energy Community

Energy Community

 

December 2009/ March 2011

completed

Development of regional and Pan-European guidelines for more efficient integration of renewable energy into future infrastructure SUSPLAN

Statkraft, Norway-Serbian office

 

December 2009/ February 2010

completed

Environmental Impact Assessment for the South Stream Project

DIEM, Russia

 

November 2009/ December 2010

completed

Regional facility for Renewable Energies and Energy Efficiency in Southeast Europe (regional RE-EE facility)-Technical Assistance to VOLKSBANK SRBIJA

KfW Entwicklungsbank, Germany 

Frankfurt School of Finance and Management, Germany;
Fichtner GmbH, Germany

July 2009/ July 2010

completed

Preparation of documentation for obtaining the Energy Permit for “Kosava” about 117 MW wind farm

MK Fintel Wind a.d., Serbia

 

June 2009/ March 2010

completed

Project Consultant - Assistance with the
implementation of the EBRD Western Balkans Sustainable Energy Direct Financing Facility (“WeBSEDFF”)

EBRD-European Bank for Reconstruction and Development

Fichtner GmbH, Germany
Energy Institute "Hrvoje Pozar", Croatia

May 2009 / mid 2012

on-going

Due diligence for four HPPs on Bistrica and Janjina Rivers

RWE, Germany

 

April 2009/ October 2009

completed

Due diligence for two PPs–Krupa and Banja Luka

RWE, Germany

 

February 2009/ March 2009

completed

Wind Potential Assessments - Kladovo Project

Decotra Srl. & EKO – KI, Italy

 

January 2009/ June 2010

completed

Wind Potential ssessments - Kula project

JP Elektroprivreda Srbije (Electric power industry of Serbia), Serbia

NetInvest d.o.o., Belgrade

January 2009/ April 2011

completed

Development and Private Sector Participation in Pljevlja Thermal Power Complex

EU European Agency for Reconstruction Podgorica, Montenegro

Fichtner GmbH, Germany

January 2009/ November 2009

completed

Wind Potential Assessments–Zabljak Project

Decotra Srl., Italy & HM Durmitor, Montenegro

 

January 2009/ July 2011

on-going

Preparation of documentation for obtaining the Energy Permit for “La Piccolina” 6 MW wind farm

MK Fintel Wind a.d., Serbia

 

December 2008/ December 2009

completed

Analysis of the potential power generation and effects of foreseen hydro power plants on the river Morača on power system of Montenegro based on updated hydrological data for the period 1986–2005

Elektroprivreda Crne Gore (EPCG)-Electric Power Industry of Montenegro, Montenegro

 

October 2008/ January 2009

completed

Technical Assistance (TA) to EMS Project Monitoring

EMS-Public Enterprise for electric energy transmission and transmission system control ''Elektromreža Srbije'' Serbian Transmission System and Market Operator, Serbia

 

September 2008/ September 2009

completed

Wind Potential Assessments–Gacko Project

Herzeg Wind, Bosnia and Herzegovina

 

September 2008/ September 2011

on-going

Due Diligence for implementation of 2-9 MWe CHP plant in Beverage Company in Belgrade

ContourGlobal Solutions Holdings Ltd., Republic of Cyprus

 

August 2008/ September 2008

completed

Modernization and Rehabilitation of Perucica HPP-Phase II, Consulting Services

KfW Entwicklungsbank, Germany

Lahmeyer International, GmbH, Germany

May 2008/ December 2009

completed

Consulting Services for the Project “Environmental Measures in Lignite Fired Power Plants”

EPS – Electric Power Industry of Serbia, Serbia

Vattenfall Europe PowerConsult GmbH, Germany

May 2008/ September 2009

completed

Due dilligence and technical solution for the construction of a CCGT 200 MWe CHP plant in the city of Kragujevac

Meinl Capital Advisors AG, Austria

 

April 2008/ June 2008

completed

Due dilligence and technical solution for the construction of 450 MWe CCGT CHP in the duty-free zone of the town of Pirot

Meinl Capital Advisors AG, Austria

 

April 2008/ June 2008

completed

TPP Turceni–Rehabilitation of Units 3 & 6-Project Justification

EBRD-European Bank for Reconstruction and
Development

 

April 2008/ June 2008

completed

Hydro and wind power strategy for selected countries in Europe

Pöyry Energy Oy, Finland

 

April 2008/ May 2008

completed

Potential HPP Kupinski Kut and HPPs Morava in the Frame of Integral Water Resources Management of the Sava River-Pre-feasibility studies

La Cardo Immobiliare S.r.l., Italy

 

March 2008/ August 2008

completed

Small Hydro Power Plants Doboj, Cijevna 5 and Cijevna 6 in Republic of Srpska–Feasibility study

Technor Energy AS, Norway

 

March 2008/ September 2008

completed

Tender documentation preparation for procurement and installation of 110kV metal–enclosed gas–insulated switchgear for new 110/35/10 kV Kotor–Škaljari Substation

EPCG-Electric Power Industry of Montenegro, Montenegro

 

March 2008/ June 2008

completed

Pre-feasibility study with conceptual design for gas fired CHP combined cycle gas turbine plant 110 MWe in Loznica town (Serbia)

Decotra S.r.l., Milan, Italy

 

November 2007/ March 2008

completed

Wind Potential Assessments–Susara Project

FINTEL Multiservizi Srl., Italy

 

November 2007/ March 2009

completed

Wind Potential Assessments–Vracev Gaj Project

FINTEL Multiservizi Srl., Italy

 

November 2007/ March 2009

completed

Wind Potential Assessments–Kruscica Project

FINTEL Multiservizi Srl., Italy

 

November 2007/ March 2009

completed

Regional facility for renewable energies and energy efficiency in Southeast Europe (regional RE-EE facility)–Technical Assistance to CACANSKA BANKA

KfW Entwicklungsbank, Germany

Frankfurt School of Finance and Management, Germany; Fichtner GmbH, Germany

September 2007/ May 2010

completed

Upgrading of 400/110/35 kV Ribarevine substation and construction of new 110/10 kV Podgorica 5 substation

EPCG-Electric Power Industry of Montenegro, Montenegro

Fichtner GmbH, Germany

July 2007/ end of 2011

on-going

Integration of Baraha 400/132 kV
Substation into DEWA 400 kV system

Fichtner GmbH, Germany

July 2007/ September 2007

completed

Pre-feasibility Study for Optimization of Water Resources Management for the Nisava River Catchment’s Area

Pirot ENERGO, Serbia

 

June 2007/ February 2008

completed

Strategic Environmental Assessment (SEA) in Connection with HPP Khudoni

World Bank, USA

 

May 2007/ October 2007

completed

Supervising Engineer for Environmental
Projects in Thermal Power Stations in Serbia

EAR - European Agency for Reconstruction

Vattenfall Europe Power Consult GmbH (VPC), Germany

March 2007/ September 2008

completed

Small Hydro Power Plants Cijevna 1, Cijevna 2, Cijevna 3 and Cijevna 4 in Republic of Srpska–Feasibility Study

TechnorEnergy AS, Norway

 

March 2007/ August 2007

completed

PSHPP Tarnita-Effects Evaluation within
Romanian and SEE Power System

World Bank, USA

 

February 2007/ May 2007

completed

Consultancy services in the process of privatization of five Small Hydro Power Plants (SHPP) in Montenegro

Private investor

 

November 2006/ February 2007

completed

Assessment of Municipal Infrastructure Agency Support Programme (MIASP)

European Commission with European Agency for
Reconstruction as an implementing agency

COWI, Denmark

October 2006/ November 2006

completed

Small Hydro Power Plants Cijevna 1, Cijevna 2 and Cijevna 4 in Republic of Srpska–Pre-Feasibility Study

TechnorEnergy AS, Norway

 

September 2006/ December 2006

completed

Feasibility study on the separation of auxiliary thermal power facilities from CHP Zrenjanin 110 MWe and transformation into district heating plant of the city of Zrenjanin

PE “Elektroprivreda Srbije”, PD Panonske TE-TO d.o.o. Novi Sad

 

August 2006/ December 2006

completed

Concession State Analysis of Small Hydro
Sites and Feasibility of Concession Granting

Enel S.p.A-International Department, Italy

 

May 2006/ July 2006

completed

Updating Generation Investment Study for South East Europe

World Bank, USA

 

May 2006/ October 2006

completed

Consultancy Services on Rehabilitation of HPP Trebinje 1

Elektroprivreda Republike Srpske (EPRS)

 

November 2005/ November 2009

completed

Technical Assistance in the Preparation
for the EIB funded Project for transmission System Rehabilitation

European Agency for Reconstruction (EAR) for EPS-Elektroistok

Fichtner GmbH, Germany

May 2005/ July 2006

completed

Feasibility Study for the Kosovo B (Kosovo)/Kashar (Albania) 400 kV Transmission Interconnection Project

UNMIK, Kosovo Trust Agency Energy Division

CESI, Italy

April 2005/ October 2006

completed

TPP Maritza East-1 (Bulgaria) Project Justification within SEE Power System

BNP Paribas and EBRD (AES Corporation)

 

April 2005/ June 2005

completed

Khuzestan ten years masterplan project

Ghods Niroo Consulting Engineers, Islamic Republic of Iran

 

February 2005/ September 2008 

completed

The Pre-Feasibility Study on Small Hydro Power Plants Potential Sites in Serbia

Italian Ministry for Environment and Territory

 

February 2005/ August 2005

completed

Study on Cogeneration of Heat and Electricity in Serbia

The International Finance Corporation-IFC

ELC and Cesi S.p.S. Italy

January 2005/ December 2005

completed